# Project Tracker Status Priority Subject Assignee Start date Due date Estimated time
597 StarHolding Group- Control room project at KIP Project New Normal Finish set and document handover process khine hein 01/17/2025 01/17/2025 Actions
572 StarHolding Group- Control room project at KIP Project New Normal Set up Power Station for control room 01/17/2025 01/17/2025 Actions
571 StarHolding Group- Control room project at KIP Project New Normal Install TVs 12/23/2024 01/23/2025 Actions
529 StarHolding Group- Control room project at KIP Project New Normal Actual Handover Documentation Process 12/10/2024 12/14/2024 Actions
528 StarHolding Group- Control room project at KIP Project New Normal Forecast Handover Documentation Process 12/10/2024 12/14/2024 Actions
527 StarHolding Group- Control room project at KIP Project New Normal Actual User Acceptance & Training Process 12/10/2024 12/14/2024 Actions
526 StarHolding Group- Control room project at KIP Project New Normal Forecast User Acceptance & Training Process 12/10/2024 12/14/2024 Actions
525 StarHolding Group- Control room project at KIP Project New Normal Monitoring and Control 12/10/2024 12/14/2024 Actions
524 StarHolding Group- Control room project at KIP Project New Normal Actual Site Cleaning Process 12/07/2024 12/14/2024 Actions
523 StarHolding Group- Control room project at KIP Project New Normal Forecast Site Cleaning Process 12/10/2024 12/14/2024 Actions
522 StarHolding Group- Control room project at KIP Project New Normal Actual Termination & Testing Process 12/07/2024 12/14/2024 Actions
521 StarHolding Group- Control room project at KIP Project New Normal Forecast Termination & Testing Process 12/07/2024 12/13/2024 Actions
520 StarHolding Group- Control room project at KIP Project New Normal Actual Electrical & AC Device Installation Process 12/07/2024 12/12/2024 Actions
519 StarHolding Group- Control room project at KIP Project New Normal Forecast Electrical & AC Device Installation Process 12/07/2024 12/12/2024 Actions
518 StarHolding Group- Control room project at KIP Project New Normal Actual Partition Painting & Door Fitting Process 12/07/2024 12/10/2024 Actions
509 StarHolding Group- Control room project at KIP Project New Normal Execution 12/07/2024 01/23/2025 Actions
508 StarHolding Group- Control room project at KIP Project New Normal Planning 12/02/2024 12/04/2024 Actions
507 StarHolding Group- Control room project at KIP Project New Normal Initiation 12/02/2024 12/02/2024 Actions
    (1-18/18)